Nashpa Oil Field

Discovery over the Nashpa structure was made in September 2009. Initially, the discovery was appraised by Early Well Testing of the discovery well Nashpa-1 and appraisal wells Nashpa-2 & 3. Later, development well Nashpa-4 was commissioned in August 2013 as gas/ oil producer. 

Drilling of exploratory well Nashpa X-5 is in progress.

Current production from Nashpa 1,2 ,3 & 4 is about 73 MMscfd gas and 19,559 bpd oil.

Field Development Plan for Nashpa was approved by the Government of Pakistan on April 19, 2013, leading to declaring its status as Development & Production Lease.