Rizq Gas Field

Rizq-1 was discovered as a tight gas reservoir in 2015.

Rizq-1 was commissioned in November 2016 and is currently producing through Rehman Production Facility.

Further Appraisal/development wells are planned to be drilled in the near future with Rizq-2 currently being drilled.

Current daily production from the well is 6.83 MMscfd**.

**Daily Production is average for 12 months from July 2016 to June 2017.