Rizq Gas Field

Rizq Gas Field

Rizq-1 was discovered as a tight gas reservoir in 2015.

Rizq-1 was commissioned in November 2016 and is currently producing through Rehman Production Facility.

Further Appraisal/development wells are planned to be drilled in the near future. Rizq-2 started drilling in May 2017 commissioned in February 2018. Rizq-3 started drilling in July 2019 and came on production on June 2020.

Current daily production from the field is 20.15 MMscfd gas & 1.29 bbl/day Codensate**.

**Daily Production is average for 06 months from July 2020 to December 2020