Nashpa Oil Field

Discovery over the Nashpa structure was made in September 2009. Initially, the discovery was appraised by Early Well Testing of the discovery well Nashpa-1 and appraisal wells Nashpa-2 & 3.  

Recently completed development wells, Nashpa-6 and Nashpa-7 have been commissioned and Nashpa-8 is being drilled.

Current production from Nashpa is about 95.313 MMscfd gas and 22,065.91 bpd oil.

Field Development Plan for Nashpa was approved by the Government of Pakistan on April 19, 2013, declaring its status as Development & Production Lease.