Mardankhel Field
Discovery over the Mardankhel structure in Tal Block was made in April 2015.
Production from discovery well Mardankhel-1 commenced in November 2016 which is being produced under early well testing.
Recently, Mardankhel-3 & Mardankhel-2 have been completed as gas and condensate producers.
Current daily production from the field is 35.58 MMscf gas, 2,062.92 bbl condensate and 22.78 tonnes LPG*.
* Daily average production is average of 6 months from July 2022 to December 2022