Maramzai Gas Field

Maramzai Gas Field

Discovery over Maramzai structure of Tal block was made in October 2009. The discovery well Maramzai-1 was connected to Manzalai Central Processing Facility for Extended Well Testing in December 2010. Production from the well commenced in January, 2011.

A total of four wells have been drilled and commissioned in Maramzai with Maramzai-4, the most recent one.

Field Development Plan of Maramzai Gas Field was approved by Government of Pakistan in April 2016, leading to declaring its status as Development & Production Lease.

Current daily production from Maramzai is about 116.80 MMscf gas, 3,743.91 barrels condensate and 112.22 tonnes LPG*.

 

* Daily production figures are averaged for 9 months from July 2021 to March 2022