Makori East Field

Makori East Field

Discovery over Makori East structure of Tal block was made in May 2011. Initially, the discovery well Makori East-1 was temporarily connected to Makori Early Production Facility for Extended Well Testing. Production from the well commenced in June 2012.

Appraisal well Makori East-2 was completed as gas/condensate producer in June 2012. Three more wells were drilled in the structure with Makori East-6, the recently completed well, has been commissioned. Field Development Plan for Makori East was approved by Government of Pakistan in October 2013, leading to declaring its status as Development & Production Lease.

Current production from Makori East is about 77.77 MMscfd gas, 8,779.16 bpd oil/condensate & 312.96 tonnes LPG* which is being processed at Makori Gas Processing Facility.

 

* Daily production figures are averaged for 9 months from July 2021 to March 2022