Adam Field
The field consists of Adam X-1, the first exploratory well in Hala Block, drilled in 2007, resulting in discovery of gas/ condensate.
To produce hydrocarbons from Adam X-1, a processing facility was installed and commissioned with first gas in December 2009.
The well initially produced from Basal formation until depletion of reservoir. Later, the workover of Adam X-1 was carried out in 2013 and the well was completed in the massive formation with initial flow of 14 MMscfd gas and 125 bpd condensate.
The field's average daily production from July 2022 to March 2023 was around 4 MMscfd gas and 58 bpd condensate.