Adam Field

The field consists of Adam X-1, the first exploratory well in Hala Block, drilled between April and June 2007, resulting in the discovery of gas/condensate.

To test Adam X-1, a processing facility was installed and commissioned with first gas in December 2009.

The well initially produced from Upper Basal Formation until depletion of reservoir in March 2013. Later, the workover of Adam X-1 was carried out between May and June 2013 and the well was completed in the Lower Basal formation with the flow rate of 14 MMscfd gas and 125 bpd condensate.

The Government of Pakistan approved the Field Development Plan for Adam X-1, declaring commerciality of its production on February 10, 2015.